Solar PV Panels on Steel Roofs: When to Require a Technical Report
Why the structure should be checked before installing solar PV panels on a steel roof: loads, wind, possible outcomes and when to commission the check.
Can the roof carry the panels?
Most steel roofs on supermarkets, warehouses and factories were designed for the weight of the roof sheeting and for the minimum maintenance live load. Installing solar PV panels adds a permanent load over the entire occupied area and changes the wind action on the roof. For this reason, the structural check should be done before the system is contracted, while it is still possible to adjust the output, the module layout and the schedule.
DeltaP Engenharia carries out this check for solar installers and for building owners, with a site inspection, a technical report and an ART. In recent years we have covered roofs of supermarkets, factories, restaurants and stores in Santa Catarina. This article describes what the check considers and presents a case in which the roof needed strengthening.

What the panels change in the structure
Permanent load
Modules, rails and fixings add weight on the order of 10 to 20 kgf per square meter, depending on the module and the mounting system. The maintenance live load adopted in the original design, usually 0.25 kN/m², refers to an occasional action and cannot be used to absorb a load that is now present at all times.
Wind
Wind action is determined in accordance with ABNT NBR 6123. Tilted panels, or panels raised above the roof sheeting, change the pressure distribution and bring suction forces to the fixings and purlins, which must also be checked for pull-out.
Local forces
The fixings transfer concentrated loads to purlins and connections that were generally designed for distributed load. Section loss from corrosion, loose connections and existing deformations reduce capacity and need to be measured in the field.
Access for maintenance
Cleaning and inspecting the modules means people walking on the roof, which requires lifelines, anchor points and work-at-height planning in accordance with NR-35. On the roofs of Baterias ERBS in Botuverá (SC), several of them with panels, we designed 305 lifelines fixed to the purlins, with a specific detail for metal roof sheeting and for fibre-cement sheeting.

How the check is done
- Roof survey: structural type, spans, purlin spacing, sections, thicknesses and condition of the connections.
- Measurement of section thickness and photographic record of each finding, with its location on the structure.
- Rebuilding the calculation model from the data collected in the field.
- Check to ABNT NBR 8800, with permanent loads, live load and wind, for the planned module layout.
- Issue of the technical report with ART, including assumptions, limitations and conditions for installation.
Possible outcomes
| Outcome | Meaning | Next step |
|---|---|---|
| Suitable | The structure carries the planned load with the required safety | Installation under the conditions of the report |
| Suitable with strengthening | Some members or connections need strengthening | Strengthening design and execution before installation |
| Not suitable | The added load is not feasible without extensive intervention | Revision of the system or choice of another area |
Case: supermarket roof with strengthening
On a supermarket roof with a span of about 20 m, the check showed that the purlins and the bracing of the roof plane did not have capacity for the added load of the panels. The strengthening design kept the existing roof trusses and purlins and added the following elements:
- rigid sag rods between the purlins and flexible sag rods in the first and last bays, for lateral restraint of the purlins;
- bracing tie rods at every second purlin, for bracing of the roof plane;
- correction of the purlin connections with angles connected to the roof truss panel points, to improve load transfer;
- verticals and diagonals in the purlins, which changed from a Vierendeel-type system to a trussed system, with a gain in stiffness and load capacity;
- rigid tie rods between the bottom chords of the roof trusses, which reduce the unbraced length of these members.


The design records an important limitation. The strengthening was sized for the maintenance live load of 0.25 kN/m² and for the added load of the panels. Bringing the whole roof into compliance with the wind actions of NBR 6123 was outside the scope, since it depends on a reassessment and global strengthening of the existing structure, and this condition is stated explicitly in the technical note on the drawing. Stating the extent of the strengthening prevents the owner from assuming that the roof was brought fully into compliance.
When to commission the check
The check should be commissioned before the solar PV system contract is signed. It is also recommended after damage events on roofs that already have panels, when there is visible corrosion, deflection or loose connections, and when the insurer, the lender or the solar installer requires the document.
What the technical report should contain
The technical report should include a description of the roof and of the survey carried out, the loads considered for the system and for wind, the design standard used for the check, the limitations of the site inspection, the conclusion and the conditions for installation. Technical responsibility is formalized in an ART.
Technical note: this article is for information only and does not replace the structural check of a specific roof. Loads, capacities and installation conditions depend on the field survey, the solar PV system adopted and the region, and must be confirmed by a qualified professional, with ART, before execution.
References
- ABNT NBR 8800: Design of steel structures and composite steel and concrete structures for buildings
- ABNT NBR 6123: Wind loads on buildings
- ABNT NBR 6120: Actions for the design of building structures
- NR-35: Work at Height (Ministry of Labor and Employment)
How to commission
Roof checks are part of diagnostic engineering for steel structures; safe access for panel maintenance is covered in lifelines and anchorage systems. For a quote, send photos of the roof, the area and the planned system output through the contact form. See also the case study on the diagnosis and retrofit of a 30,600 m² industrial building.