Vertical Access to the Tumbler Elevator Requires Integrated Protection

This article presents a vertical ladder for access to the tumbler elevator, designed by DeltaP Engenharia with a cage of protection, fixations along the existing beams of the equipment, and a life line in steel cable. The solution was conceived to allow access up to the roof, at an approximate height of 8,400 mm, keeping the worker protected from the beginning to the end of the journey.

The ladder, the cage, the supports, and the life line must be used as an integrated system. The cage is a measure of collective protection against lateral egress and does not replace the fall protection system when there is a risk of falling during ascent, descent, or transit to the roof.

DeltaP provides services for access project designs, life lines, and anchorage systems for industrial installations, from field erection to the specification of each component of the line — cable, hooks, safety shoes, and anchorage points — in a coherent manner with the protective equipment that the worker will effectively use. NR-35 requires planning, organization, risk analysis, definition of systems and anchorage points, selection and inspection of equipment, supervision, and planning of rescue. [1]

Isometric view of the ladder with the cage and life line of the tumbler elevator

Figure 1 — Isometric view of the ladder, the cage of protection, and the elements of fixation of the tumbler elevator.

System Access Configuration

The isometric view shows the stairs installed alongside the vertical structure of the elevator. The cage follows the protective section along the access and has horizontal rings distributed along the height. The stair supports are connected to the existing structure, following the orientation to adjust the fixation together with the elevator beams.

The project identifies points X, Y, and Z to detail the connections and assembly of the components. The color legend differentiates the new structure, the existing structure, and the life line cable. This identification facilitates the check during assembly, but does not replace the dimensional control and inspection of the installed pieces.

The solution also provides access to the roof. Before release, it is necessary to evaluate the transition between the stairs and the roof, the presence of edges, openings, equipment, inclined or slippery surfaces, and the available free fall distance.

Steel Cable and Specified Components

The technical specification records a segment of galvanized steel cable of 3/8” (9.52 mm), type 6×19, with independent steel core, with a length of 8.5 m. It also indicates six heavy-duty clamps for cable of 3/8” and two cleats for cable of the same diameter.

The presence of these items does not authorize substitutions without validation. The cable, the clamps, the cleats, the fixing points, the fall arresters, and the harness must be compatible with each other. The fall protection equipment must be selected to work with the type, diameter, and configuration of the specified line.

The specification explicitly determines that the line must be used with fall arresters and that a lanyard must not be used to make a direct connection between the operator and the line. This instruction must be incorporated into the operational procedure and communicated to authorized workers.

Top view, execution notes, installation of clamps and materials list

Figure 2 — Top view, execution notes, color legend, and project materials list.

Fixation along existing beams

Detail Z indicates that the staircase fixation must be adjusted in conjunction with the existing elevator beams. This condition requires the real geometry to be surveyed, the available beams to be identified, and the capacity of the elements that will receive the loads to be verified.

The elevator structure and other existing equipment are outside the structural analysis indicated in the project. The contractor must provide the necessary verifications and interventions before execution. It is not recommended to cut, drill, weld, or move elevator components without an assessment by the responsible technical person for the equipment and structure.

The 200 mm dimension indicated in detail Z must be verified in the real condition. The project dimensions are a reference for fabrication and assembly, but they must be validated on-site before execution, as per the project's technical notes.

Details of staircase fixation and assembly of life line components

Figure 3 — Details X, Y and Z of the fixations and associated components of the life line.

Protection Cage and Access Dimensions

The cut A–A shows a protection cage with approximately 6,300 mm, and also indicates the height up to the roof as approximately 8,400 mm. The project also presents reference dimensions for the start of access, including sections of 2,000 mm, 293 mm, and 184 mm, which should be compared with the final geometry of the equipment.

The cage must remain continuous, stable, and free of deformations that reduce passage. Its rings and uprights cannot create points of entrapment, interfere with the fall-arrest system, or hinder the connection and safe movement of the worker.

The cage does not eliminate the need for connection to the fall-protection system. The worker must use a parachute-type harness and a compatible fall-arrest system from the start of the activity until reaching an effectively protected area. The risk analysis should define the sequence of connection and disconnection during the transition to the roof.

Cut A–A with protection cage, heights, and life line cable

Figure 4 — Cut A–A and representation of the vertical path of the life line cable.

Installation of Bolts and Torque Control

The installation detail for the bolts indicates the use of a shoe, the arrangement of the bolts, and the reference torques presented in the own drawing. These values should be confirmed with the manufacturer of the model actually provided and applied with a calibrated tool.

The inspection of the installation should verify the quantity of bolts, the position of the pieces, the seating of the cable in the shoe, the tightening, the absence of crushing or deformation of the cable, and the correct orientation of the components. The torque indicated for a specific model should not be automatically transferred to another component.

After the completion of the entire installation, the specification determines the tensioning of the cable. The tensioning should be carried out by a qualified professional or under their responsibility, with a record of the procedure and the final condition of the system.

Inspection and Maintenance

The inspection should cover the cable along its entire length, the terminals, the cleats, the nails, the stair supports, the cage, the welds, the bolts, the elevator beams, and the transition areas to the roof.

Broken wires, corrosion, folds, compressions, damage to the web, deformations, looseness, cracks, section loss, and signs of overload should be sought. The elevator structure should be inspected for changes, vibration, corrosion, and interventions that may have affected the fixations.

The specification requires periodic inspection of the life line by a qualified professional at a maximum interval of 12 months. This period should be incorporated into the control program, without excluding inspection before use, after abnormal events, and whenever there is doubt about the integrity of the system. Environmental conditions, the manufacturer, and risk analysis may require a higher frequency.

After a significant drop or impact, the system should be taken out of service until a formal assessment is made. The line should not be released based solely on an informal visual inspection or a new tightening of the cleats.

Safety Requirements

Access must be performed by a formally authorized, trained, and qualified worker for work at height. The procedure should include isolation of the area, risk of falling tools, communication, supervision, weather conditions, equipment blocking or control when applicable, and a rescue plan.

The NR-35 requires that the risk analysis consider the location and its surroundings, anchorage systems and points, weather conditions, selection and inspection of the protection systems, impediment conditions, and emergency situations. [1]

The ABNT NBR 16325 series should be consulted in the current edition for the applicable requirements to the anchorage devices. Also, the technical standards relevant to the parachute harness, connectors, absorbers, and fall arresters should be observed. Compliance does not result from a single component: it depends on the set formed by structure, line, equipment, installation, use, and maintenance. [3]

ConclusĂŁo

DeltaP specializes in the design and execution of access, life lines, and anchoring systems for elevators, dumpers, silos, and other industrial environments. The company's unique advantage lies in treating each component—stairs, cage, cable, fasteners, and fall arresters—as part of a single, detailed, and specified system, with the same rigor applied to a structural project: field survey, solution definition, fastener detailing, component specification, installation, inspection, and technical documentation.

The analyzed solution features a vertical access configuration for the dumper elevator with stairs, a protective cage, and a life line in a 8.5-meter galvanized steel cable. The critical execution points are the fastening to the existing beams, the compatibility of the fall arresters, the correct installation of the clamps, the final tensioning, and the safe transition to the roof.

Installation must only be authorized after confirming the measurements on-site, evaluating the elevator structure, executing by competent professionals, documenting the inspection, and integrating the system with the height work procedure and rescue plan.

Technical Note: This article interprets the provided drawing for informational and technical communication purposes. It does not replace the execution project, structural analysis, risk analysis, manufacturer instructions, inspection by a qualified professional, or the required installation documentation. Dimensions, capacities, materials, torques, and usage conditions must be confirmed on-site and in the official documentation before execution.

References

  1. NR-35 — Work at Heights, official current text
  2. NR-01 — General Dispositions and Occupational Risk Management
  3. NBR 16325-1 and NBR 16325-2: protection against falls from heights
#Linha de Vida#NR-35#Elevador Tombador#Trabalho em Altura#Escada com Gaiola#Ancoragem

Need a technical report or project?

Describe the case and send photos. We return with scope, deadline, and value.

Request quotation